As per Kuwait Times, Deputy CEO for Projects at Kuwait National Petroleum Company (KNPC) Abdullah Al-Ajmi pointed out the importance of reducing costs and increasing work efficiency.
He expressed intentions to help realize that after assuming his new post by achieving more integration between the three projects under him: the clean fuel project, the project circuit 1 and the project circuit 2.
He said the current structure at the projects’ sector is enough to run projects today and during the next three years, adding that 50 percent of the clean fuel project will be completed by the end of March. Ajmi said that by April 13, 24 months would have elapsed on the strategic project’s signing.
“This reflects our success in going on with the plan as we prepare to go ahead with the construction stages after completing the engineering works this month,” he said.